Empanelled with MoRTH under
Category IV : GeoTechnical Investigation
B. Seenaiah & Co. (Projects) Ltd., Haydrabad
Complete Project

1. Widening of existing two lanes to four lanes divided carriageway facility including rehabilitation of existing two lane from Km. 208 to 251.7(package 6 ) on Ayodhya - Gorakhpur section of NH- 28 in U.P.

Project Type: Sub-Soil Investigation

Contract Value: 6,00,000.00

Project Detail
For ground improvement work for fly over at Km. 233 + 726 and for R.O.B at Km. 244 + 200 in packages WB-6, NH- 28.

Authority Under Whom Executed
B.Seenaiah & Company (Projects) Ltd.
Head office: 6-2-913/ 914, 5th. Floor Progressive Towers, Khairtabad Hyderabad- 500 004(A.P.) +91-40-23303663

Time Taken: 2 Month

Remarks:All preliminary testing of soil before and after groung improvement which includes soil properties like atterbergs limits, sieving, specific gravity, permeability shear and consolidation and SPT, DCPT and submission of test report.

Clients

Techpro Engineers Pvt. Ltd. © 2015. All Rights Reserved.